CamoTEXtreme is structured around seven work packages that run in overlapping, iterative phases. Management runs throughout; requirements and technology surveys feed into core R&D; integration, testing and producibility close the loop.
Timeline (Gantt Chart)
| WP | Leader | Start | End | Timeline (M0 to M36) |
|---|---|---|---|---|
| WP100 | PDOT | M0 | M36 |
WP100 (36 mo)
|
| WP200 | WAT | M0 | M6 |
WP200
|
| WP300 | FORTH | M0 | M18 |
WP300
|
| WP400 | LIST | M5 | M28 |
WP400
|
| WP500 | UGent | M12 | M33 |
WP500
|
| WP600 | RINA | M14 | M34 |
WP600
|
| WP700 | LRT | M24 | M33 |
WP700
|
Work Package Details
WP 100: Project Management
Leader: PDOT | Duration: 36 months
Coordination of the entire consortium: technical management, project reporting, and dissemination and exploitation of results.
- Technical coordination
- Progress reporting
- Dissemination activities
- Progress reports every 6 months
- Final report (M36)
WP 200: Operational requirements
Leader: WAT | Duration: 6 months
Defines military requirements, operational environments, and sets test protocols and performance metrics.
- Military camo requirements
- Operational environment definitions
- Test procedures
- Requirements reports
- Test procedure definitions
WP 300: Technologies and materials advancements
Leader: FORTH | Duration: 18 months
A deep state-of-the-art survey across sensor threats, camouflage materials, and smart-textile multifunctionalisation.
- Threats and sensor survey
- Nanotechnology for textiles
- Smart textiles SoA
- SoA material reports
- SoA testing with manikins
WP 400: R&D on multifunctional adaptive camouflage
Leader: LIST | Duration: 23 months
Core R&D: new mimetic patterns, advanced formulations for multispectral camouflage, and C4I system interfacing.
- Mimetic pattern design
- Multispectral formulations
- C4I interface design
- Reports on patterns & formulations
- Smart-textile R&D reports
WP 500: R&D on systems integration
Leader: UGent | Duration: 21 months
Prototype integration, global proof-of-concept ensembles, and design simulations.
- CAD solution design
- Systems integration
- Global PoC assembly
- Integration reports
- Global PoC integration report
WP 600: Testing and evaluation
Leader: RINA | Duration: 20 months
Lab and field assessment of camouflage efficiency, comfort, and thermoregulation.
- Laboratory mechanical tests
- Manikin trials
- Field trials (forest/urban)
- Lab evaluation reports
- Field trial results
WP 700: Producibility
Leader: LRT | Duration: 9 months
Manufacturability and industrial scale-up cost studies for finished textile products.
- Fabric cost study
- Manufacturing scale-up
- Cost prediction reports
- Scale-up manufacturing report
Contractual Milestones
| Milestone | Date | Description |
|---|---|---|
| M1 | T0 + 6 | 1st Progress Review |
| M2 | T0 + 12 | 2nd Progress Review |
| M3 | T0 + 18 | 3rd Progress Review |
| M4 | T0 + 24 | 4th Progress Review |
| M5 | T0 + 30 | 5th Progress Review |
| M6 | T0 + 36 | Final Meeting and Demo |